July 29, 2025
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
July 24, 2025
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
July 4, 2025
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
June 30, 2025
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
May 7, 2025
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
February 27, 2025
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
January 20, 2025
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
December 12, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
November 7, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
October 24, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
September 6, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
August 29, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
July 31, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
June 4, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
March 8, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
January 30, 2024
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
December 6, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
November 13, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
October 11, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
September 20, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
August 2, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
July 7, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
May 16, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
April 4, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
March 1, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
February 1, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
January 11, 2023
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
December 2, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
November 24, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
October 14, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
September 2, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
August 10, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
July 11, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
June 27, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
May 16, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
April 4, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
March 2, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
February 3, 2022
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
September 2, 2021
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
August 9, 2021
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
Warehouse Lofts Toronto construction update
x  |  Construction Update – Aug 9, 2021
x  |  Construction Update – Aug 9, 2021
x  |  Construction Update – Aug 9, 2021
x  |  Construction Update – Sept 2, 2021
x  |  Construction Update – Sept 2, 2021
x  |  Construction Update – Sept 2, 2021
x  |  Shoring Has Started – Feb 1, 2022
x  |  Shoring Has Started – Feb 1, 2022
x  |  Shoring Has Started – Feb 1, 2022
x  |  Shoring Continues – Feb 24, 2022
x  |  Shoring Work Continues – March 2, 2022
x  |  Shoring Work Continues – March 2, 2022
x  |  Shoring Work Continues – March 2, 2022
x  |  Shoring Work Continues – April 4, 2022
x  |  Shoring Work Continues – April 4, 2022
x  |  Shoring Work Continues – April 4, 2022
x  |  May 16, 2022
x  |  May 16, 2022
x  |  May 16, 2022
x  |  June 27, 2022
x  |  June 27, 2022
x  |  June 27, 2022
x  |  July 11, 2022
x  |  July 11, 2022
x  |  July 11, 2022
x  |  August 10, 2022 – Excavation Continues.
x  |  August 10, 2022 – Shaving of King and Filler Piles.
x  |  August 10, 2022 – Lagging Work Along the West Side of the Property.
x  |  September 2, 2022 – Finishing off the Walers and Lagging Work
x  |  September 2, 2022 – Finishing off the Walers and Lagging Work
x  |  September 2, 2022 – Finishing off the Walers and Lagging Work
x  |  October 14, 2022 – Blindside waterproofing followed by shotcrete work continues
x  |  October 14, 2022 – Verticals being formed and precast sump pits are placed
x  |  October 14, 2022 – Aerial view showing verticals completed and rebar columns ready for forms
x  |  November 24, 2022 – Slab On Grade 50% Complete
x  |  November 24, 2022 – Slab On Grade 50% Complete
x  |  November 24, 2022 – Slab On Grade 50% Complete
x  |  December 2, 2022 – Table Forms in place for P1 structural slab.
Back fill of the southwest side under the Colonnade.
x  |  December 2, 2022 – View looking East from Slab On Grade.
x  |  December 2, 2022 – Aerial view capturing preparation for balance of SOG and Table Forms for P1 structural slab.
x  |  January 11, 2023 – Waterproofing has started from P1 to grade.
x  |  January 11, 2023 – Cross Braces P2 to P1 being cut.
x  |  January 11, 2023 – Ramp from P1 to P2 complete.
x  |  February 1, 2023 –Forming elevator shaft, from P1 to grade
x  |  February 1, 2023 –South perimeter wall formed and stripped, from P1 to grade
x  |  February 1, 2023 –Rebar placed in front of waterproofing on the east perimeter wall, from P1 to grade
x  |  March 1, 2023 – Deck for ramp from P1 to Ground level well underway
x  |  March 1, 2023 – Perimeter wall P1 to Ground level on east side now complete
x  |  March 1, 2023 – Storm water tank floor complete
x  |  April 4, 2023 – Second pour of Ramp completed
x  |  April 4, 2023 – Northwest section, rebar for Grade Beam now in place
x  |  April 4, 2023 – Northeast side ready to receive waterproofing
x  |  May 16, 2023 – Verticals are being formed from Ground to Second Level
x  |  May 16, 2023 – Ground Floor Slab now complete
x  |  May 16, 2023 – Forming in place for the East Perimeter Wall, from Ground to Mezzanine Level
x  |  July 7, 2023 – Current form of Parliament & Co. from Parliament Street showing verticals forms from Level 2 to Level 3 have started
x  |  July 7, 2023 – Final rebar for Level 2 has arrived, awaiting placement before the concrete pour
x  |  July 7, 2023 – Second pour for Level 2 started
x  |  August 2, 2023 – First pour for Level 3 completed along the West Side
x  |  August 2, 2023 – Level 3 East Side floor decking and capital forming underway
x  |  August 2, 2023 – Main Level stripping of the concrete slab and reshoring
x  |  September 20, 2023 – South Elevation revealing the large expansive openings for the Warehouse inspired-windows
x  |  September 20, 2023 – North Elevation showing the garage entrance from Anna Hillard Lane
x  |  September 20, 2023 – West Elevation indicating the completion of the 4th level structural slab
x  |  October 11, 2023 – Guard rails installed in preparation of work to begin on above grade
x  |  October 11, 2023 – Piping installation continues below grade
x  |  October 11, 2023 – Block work started below grade
x  |  November 13, 2023 – Top and Bottom Rebar placement continues for 7th Level Slab
x  |  November 13, 2023 – Steel HSS work has started, fastened below the 2nd Level Slab
x  |  November 13, 2023 – Masonry block work continues on Level P1
x  |  December 6, 2023 – HSS work along the Eastside perimeter wall completed on Level 2
x  |  December 6, 2023 – Decking and placing bottom rebar continues for Level 8. Conduit works initiated
x  |  December 6, 2023 – Duct work well underway below grade, along with hanging pipe for drains and erecting masonry block walls
x  |  January 30, 2024 – DensGlass on steel stud installation started on the sixth level, facing North and West
x  |  January 30, 2024 – Hoist installation complete on the North side entrance off Anna Hilliard Lane
x  |  December 6, 2023January 30, 2024 – Steel stud erection on the perimeter of the 6th Level completed, image shown is facing south
x  |  March 8, 2024 – Densglass and Blueskin work on the perimeter has started
x  |  March 8, 2024 – Curtain wall window frames have started on the main level
x  |  March 8, 2024 – South facade revealing the progress with Densglass and Blueskin
x  |  June 4, 2024 – Stripping of previously poured concrete columns, allows forms to be reused for the balance of verts from level 10 to 11
x  |  June 4, 2024 – Stripping of previously poured concrete columns, allows forms to be reused for the balance of verts from level 10 to 11
x  |  June 4, 2024 – Stripping of previously poured concrete columns, allows forms to be reused for the balance of verts from level 10 to 11
x  |  July 31, 2024 – In preparation for pouring the Mechanical Penthouse Level
x  |  July 31, 2024 – In preparation for pouring the Mechanical Penthouse Level
x  |  July 31, 2024 – In preparation for pouring the Mechanical Penthouse Level
x  |  August 29, 2024 – Waterproofing on Level 4 started
x  |  August 29, 2024 – 11th Level Event Space View Facing West
x  |  August 29, 2024 – Window Installation facing West on Level 2
x  |  September 6, 2024 – Interior studwork for demising walls has started
x  |  September 6, 2024 – Insulation with vapour barrier added once the exterior windows are fully caulked
x  |  September 6, 2024 – Drywall added to the demising walls in preparation of acoustic ceiling placement
x  |  October 24, 2024 – West Face exterior cladding completed from Levels 4-7
x  |  October 24, 2024 – Window installation continues on the East Face Level 6
x  |  October 24, 2024 – Gold Seal application completed on the South Face
x  |  November 7, 2024 – Waterproofing of the roof almost completed
x  |  November 7, 2024 – Installation of the curtain wall for the event space started
x  |  November 7, 2024 – Batt insulation for the demising walls between lofts well underway
x  |  December 12, 2024 – Installation of the south side insulation completed - preparation for the scratch coat to follow
x  |  December 12, 2024 – Curtainwall supports on the south side for the 11th level Event Space well underway
x  |  December 12, 2024 – Drywall placement along the demising walls to the perimeter wall nearing completion
x  |  January 20, 2025 – Insulation and drywall continues on the work-live lofts
x  |  January 20, 2025 – The final cage detail now installed in the HV Transformer Room
x  |  January 20, 2025 – Layouts within the lofts progressing well related to the placement of interior studs
x  |  February 27, 2025 – Installation of bathrooms started
x  |  February 27, 2025 – Elevator installation progressing well
x  |  February 27, 2025 – VRF Units erected just below the acoustic abatement ceiling channels
x  |  May 7, 2025 – Cladding work on levels 2 and 3 continues
x  |  May 7, 2025 – Drywall work well underway
x  |  May 7, 2025 – Perimeter flashing work on terraces continues
x  |  July 2, 2025 – View from Parliament Street facing Northeast
x  |  July 2, 2025 – View from Parliament Street facing East
x  |  July 2, 2025 – View from Parliament Street facing Southeast
x  |  July 4, 2025 – The event space
x  |  July 4, 2025 – Exterior terrace of the event space
x  |  July 4, 2025 – Loft interior
x  |  July 24, 2025 – View from Parliament Street facing East
x  |  July 24, 2025 – View from Parliament Street facing Northeast
x  |  July 24, 2025 – View from Myer Willinsky Lane facing Northwest
x  |  July 29, 2025 – View from Parliament Street facing Northeast
x  |  July 29, 2025 – Exterior view of the rooftop event space
x  |  July 29, 2025 – View from Parliament Street facing East