Now Under Construction
March 18, 2024
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 8, 2024
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
January 30, 2024
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
December 6, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
November 27, 2023

Currently Forming Level 8

November 27th, 2023

November 13, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
October, 2023

Aerial view of the perimeter for Warehouse Lofts Toronto

October 11th, 2023

October 11, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 29, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 27, 2023

Aerial view of the West perimeter for Warehouse Lofts Toronto

September 27th, 2023

Aerial view of the East perimeter for Warehouse Lofts Toronto

September 27th, 2023

September 27, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 26, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 20, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
August 30, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
August 14, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
August 2, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
July 21, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
July 14, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
July 7, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
June 29, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
June 13, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
June 7, 2023
Warehouse Lofts East Section 360° Video
Warehouse Lofts Aerial Video
May 25, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
May 16, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
April 17, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
April 12, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
April 4, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 31, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 30, 2023

Aerial view of the perimeter for Warehouse Lofts Toronto

March 30th, 2023

March 28, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 21, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 15, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 14, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 9, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 7, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 6, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 2, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 1, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
February 28, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
February 17, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
February 14, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
February 13, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
February 8, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
February 1, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
January 25, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
January 24, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
January 23, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
January 18, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
January 16, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
January 11, 2023
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
December 7, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
December 2, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
November 24, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
October 14, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 23, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 16, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 2, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
August 31, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
August 29, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
August 10, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
July 11, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
June 27, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
May 16, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
April 29, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
April 4, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 16, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
March 2, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
February 18, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
February 3, 2022
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 13, 2021
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
Warehouse Lofts Toronto Construction Update
September 2, 2021
September 2 Construction
September 2 Construction
September 2 Construction
August 27, 2021
August 27 Construction
August 27 Construction
August 27 Construction
August 13, 2021
August 11 Construction
August 11 Construction
August 11 Construction
August 9, 2021
August 9 Construction
August 9 Construction
August 9 Construction
August 6, 2021
July 30, 2021
July 20, 2021
July 12, 2021
x  |  Construction Update – July 7, 2021
x  |  Construction Update – July 7, 2021
x  |  Construction Update – July 7, 2021
x  |  Construction Update – July 8, 2021
x  |  Construction Update – July 8, 2021
x  |  Construction Update – July 8, 2021
x  |  Construction Update – July 12, 2021
x  |  Construction Update – July 12, 2021
x  |  Construction Update – July 12, 2021
x  |  Construction Update – July 13, 2021
x  |  Construction Update – July 13, 2021
x  |  Construction Update – July 13, 2021
x  |  Construction Update – July 20, 2021
x  |  Construction Update – July 20, 2021
x  |  Construction Update – July 20, 2021
x  |  Construction Update – July 21, 2021
x  |  Construction Update – July 21, 2021
x  |  Construction Update – July 21, 2021
x  |  Construction Update – July 23, 2021
x  |  Construction Update – July 23, 2021
x  |  Construction Update – July 23, 2021
x  |  Construction Update – July 26, 2021
x  |  Construction Update – July 26, 2021
x  |  Construction Update – July 26, 2021
x  |  Construction Update – July 28, 2021
x  |  Construction Update – July 28, 2021
x  |  Construction Update – July 28, 2021
x  |  Construction Update – July 30, 2021
x  |  Construction Update – July 30, 2021
x  |  Construction Update – July 30, 2021
x  |  Construction Update – Aug 4, 2021
x  |  Construction Update – Aug 4, 2021
x  |  Construction Update – Aug 4, 2021
x  |  Construction Update – Aug 6, 2021
x  |  Construction Update – Aug 6, 2021
x  |  Construction Update – Aug 6, 2021
x  |  Construction Update – Aug 9, 2021
x  |  Construction Update – Aug 9, 2021
x  |  Construction Update – Aug 9, 2021
x  |  Construction Update – Aug 11, 2021
x  |  Construction Update – Aug 11, 2021
x  |  Construction Update – Aug 11, 2021
x  |  Construction Update – Aug 11, 2021
x  |  Construction Update – Aug 11, 2021
x  |  Construction Update – Aug 11, 2021
x  |  Construction Update – Aug 24, 2021
x  |  Construction Update – Aug 24, 2021
x  |  Construction Update – Aug 24, 2021
x  |  Construction Update – Aug 27, 2021
x  |  Construction Update – Aug 27, 2021
x  |  Construction Update – Aug 27, 2021
x  |  Construction Update – Aug 31, 2021
x  |  Construction Update – Aug 31, 2021
x  |  Construction Update – Aug 31, 2021
x  |  Construction Update – Sept 2, 2021
x  |  Construction Update – Sept 2, 2021
x  |  Construction Update – Sept 2, 2021
x  |  Construction Update – Sept 7, 2021
x  |  Construction Update – Sept 7, 2021
x  |  Construction Update – Sept 7, 2021
x  |  Construction Update – Sept 13, 2021
x  |  Construction Update – Sept 13, 2021
x  |  Construction Update – Sept 13, 2021
x  |  Shoring Has Started – Feb 1, 2022
x  |  Shoring Has Started – Feb 1, 2022
x  |  Shoring Has Started – Feb 1, 2022
x  |  Shoring Continues – Feb 10, 2022
x  |  Shoring Continues – Feb 10, 2022
x  |  Shoring Continues – Feb 10, 2022
x  |  Shoring Continues – Feb 18, 2022
x  |  Shoring Continues – Feb 18, 2022
x  |  Shoring Continues – Feb 18, 2022
x  |  Shoring Continues – Feb 24, 2022
x  |  Shoring Continues – Feb 24, 2022
x  |  Shoring Continues – Feb 24, 2022
x  |  Shoring Work Continues – March 2, 2022
x  |  Shoring Work Continues – March 2, 2022
x  |  Shoring Work Continues – March 2, 2022
x  |  Shoring Work Continues – March 10, 2022
x  |  Shoring Work Continues – March 10, 2022
x  |  Shoring Work Continues – March 10, 2022
x  |  Shoring Work Continues – March 16, 2022
x  |  Shoring Work Continues – March 16, 2022
x  |  Shoring Work Continues – March 16, 2022
x  |  Shoring Work Continues – March 21, 2022
x  |  Shoring Work Continues – March 21, 2022
x  |  Shoring Work Continues – March 21, 2022
x  |  Shoring Work Continues – April 4, 2022
x  |  Shoring Work Continues – April 4, 2022
x  |  Shoring Work Continues – April 4, 2022
x  |  Shoring Work Continues – April 18, 2022
x  |  Shoring Work Continues – April 18, 2022
x  |  Shoring Work Continues – April 18, 2022
x  |  Shoring Work Continues – April 29, 2022
x  |  Shoring Work Continues – April 29, 2022
x  |  Shoring Work Continues – April 29, 2022
x  |  Shoring Work Continues – May 5, 2022
x  |  Shoring Work Continues – May 5, 2022
x  |  Shoring Work Continues – May 5, 2022
x  |  May 16, 2022
x  |  May 16, 2022
x  |  May 16, 2022
x  |  June 27, 2022
x  |  June 27, 2022
x  |  June 27, 2022
x  |  July 6, 2022
x  |  July 6, 2022
x  |  July 6, 2022
x  |  July 8, 2022
x  |  July 8, 2022
x  |  July 8, 2022
x  |  July 11, 2022
x  |  July 11, 2022
x  |  July 11, 2022
x  |  July 19, 2022
x  |  July 19, 2022
x  |  July 19, 2022
x  |  August 10, 2022 – Excavation Continues.
x  |  August 10, 2022 – Shaving of King and Filler Piles.
x  |  August 10, 2022 – Lagging Work Along the West Side of the Property.
x  |  August 29, 2022 – Crane Pad Completed
x  |  August 29, 2022 – Crane Pad Completed
x  |  August 29, 2022 – Crane Pad Completed
x  |  August 31, 2022 – CRANE IS ERECTED
x  |  August 31, 2022 – CRANE IS ERECTED
x  |  August 31, 2022 – CRANE IS ERECTED
x  |  September 2, 2022 – Finishing off the Walers and Lagging Work
x  |  September 2, 2022 – Finishing off the Walers and Lagging Work
x  |  September 2, 2022 – Finishing off the Walers and Lagging Work
x  |  September 16, 2022 – Water Proofing and Footing Formation Continues
x  |  September 16, 2022 – Water Proofing and Footing Formation Continues
x  |  September 16, 2022 – Water Proofing and Footing Formation Continues
x  |  September 23, 2022 – Detailed Excavation Showing Elevator and Stair Locations
x  |  September 23, 2022 – Crane on Site
x  |  September 23, 2022 – Detailed Excavation Facing South
x  |  October 14, 2022 – Blindside waterproofing followed by shotcrete work continues
x  |  October 14, 2022 – Verticals being formed and precast sump pits are placed
x  |  October 14, 2022 – Aerial view showing verticals completed and rebar columns ready for forms
x  |  November 24, 2022 – Slab On Grade 50% Complete
x  |  November 24, 2022 – Slab On Grade 50% Complete
x  |  November 24, 2022 – Slab On Grade 50% Complete
x  |  December 2, 2022 – Table Forms in place for P1 structural slab.
Back fill of the southwest side under the Colonnade.
x  |  December 2, 2022 – View looking East from Slab On Grade.
x  |  December 2, 2022 – Aerial view capturing preparation for balance of SOG and Table Forms for P1 structural slab.
x  |  December 7, 2022 – Rebar placement underway for P1 structural slab.
x  |  December 7, 2022 – Rebar placement on table forms for P1, eastern section.
x  |  December 7, 2022 – Balance of Slab On Grade now 100% complete.
x  |  January 11, 2023 – Waterproofing has started from P1 to grade.
x  |  January 11, 2023 – Cross Braces P2 to P1 being cut.
x  |  January 11, 2023 – Ramp from P1 to P2 complete.
x  |  January 11, 2023 – Aerial drone image.
x  |  January 11, 2023 – Waterproofing from P1 to ground underway.
x  |  January 11, 2023 – Verticals from P1 to ground underway.
x  |  January 16, 2023 – Verticals for P1 to grade looking West.
x  |  January 16, 2023 – Pile chipping on the North side started.
x  |  January 16, 2023 – Rebar placement for South side perimeter wall after waterproofing.
x  |  January 18, 2023 – Form work continues to grade
x  |  January 18, 2023 – Perimeter rebar work continues to grade on the south side
x  |  January 18, 2023 – Forming stairwell on the southeast side of the property
x  |  January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x  |  January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x  |  January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x  |  January 24, 2023 – Pile chipping on the north side continues for the ground floor slab
x  |  January 24, 2023 – Waterprofing completed and rebar placement on the south parimeter wall started
x  |  January 24, 2023 – Waterprofing completed and rebar placement on the west parimeter wall started
x  |  January 25, 2023 – Placing rebar for garage ramp wall P1 to grade
x  |  January 25, 2023 – Installing inside form box for elevator, to receive rebar
x  |  January 25, 2023 – Placing rebar for garage ramp wall P1 to grade
x  |  February 1, 2023 –Forming elevator shaft, from P1 to grade
x  |  February 1, 2023 –South perimeter wall formed and stripped, from P1 to grade
x  |  February 1, 2023 –Rebar placed in front of waterproofing on the east perimeter wall, from P1 to grade
x  |  February 8, 2023 – Forming elevator shaft, from P1 to grade
x  |  February 8, 2023 – North wall waterproofing completed and rebar started, from P1 to grade
x  |  February 8, 2023 – East wall showing rebar in place in front of waterproofing, from P1 to grade
x  |  February 13, 2023 – Rebar placement started in front of waterproofing on the north side
x  |  February 13, 2023 – Rebar placement on the south side perimeter wall continues
x  |  February 13, 2023 – Below grade piping for drains has started
x  |  February 14, 2023 – In preparation for slab on grade required rebar is on site
x  |  February 14, 2023 – Overall view looking west showing current site condition
x  |  February 14, 2023 – North wall ready to receive forms, showing rebar and waterproofing completed
x  |  February 17, 2023 – Tables for ground floor slab and beams below
x  |  February 17, 2023 – Shotcrete completed on south wall P1 to grade. Rebar visible for ramp, from ground to P1
x  |  February 17, 2023 – Tables and rebar shown for the Storm Water Tank base located at the south west corner
x  |  February 28, 2023 – Building forms for ground floor structural slab
x  |  February 28, 2023 – View looking west showing site progress
x  |  February 28, 2023 – Preparation underway for buildout of ramp from Ground to P1
x  |  March 1, 2023 – Deck for ramp from P1 to Ground level well underway
x  |  March 1, 2023 – Perimeter wall P1 to Ground level on east side now complete
x  |  March 1, 2023 – Storm water tank floor complete
x  |  March 2, 2023 – Image looking northeast showing the ramp
x  |  March 2, 2023 – View looking east showing the perimeter wall on the east side completed, from P1 to Ground
x  |  March 2, 2023 – Rebar placement for transfer beams related to Ground floor slab underway
x  |  March 6, 2023 – Rebar placement for ramp, Ground to P1 70% complete
x  |  March 6, 2023 – Additional section for the ramp from Ground to P1 shown on the southeast corner
x  |  March 6, 2023 – Preparation for waterproofing has begun on the northwest side
x  |  March 7, 2023 – Rebar placement for Ground floor slab continues
x  |  March 7, 2023 – View of rebar on ramp from P1 to Ground
x  |  March 7, 2023 – Pipes and drains being installed below grade
x  |  March 9, 2023 – P1 to Ground ramp first pour complete
x  |  March 9, 2023 – In preparation of grade beam at the northwest corner
x  |  March 9, 2023 – Rebar placement for ground floor slab continues
x  |  March 14, 2023 – Conduits now being installed for Pour 1 of Ground floor slab
x  |  March 14, 2023 – Forms are being extended for Pour 2 of the ramp towards the eastern corner, from P1 to Ground
x  |  March 14, 2023 – Precast stairs now being installed below grade
x  |  March 15, 2023 – Wall forms being placed for storm water tank
x  |  March 15, 2023 – Additional conduit being installed for Ground floor slab, pour 1
x  |  March 15, 2023 – Northwest side showing waterproofing and nelson studs in preparation for grade beam
x  |  March 21, 2023 – Forms for ramp continue from the east corner heading north
x  |  March 21, 2023 – Forms for ramp continue from the east corner heading north
x  |  March 21, 2023 – Forms for ramp continue from the east corner heading north
x  |  March 28, 2023 – Rebar added for second pour of Ramp Section
x  |  March 28, 2023 – Conduits added to a pour for Ground Floor Slab
x  |  March 28, 2023 – Rebar placed for Grade Beam pour 1 Ground Floor Slab
x  |  March 31, 2023 – Second pour for Ramp complete
x  |  March 31, 2023 – Preparation for balance of Grade Beam almost complete
x  |  March 31, 2023 – Concrete Matt for pour 1 of Ground Floor Slab complete
x  |  April 4, 2023 – Second pour of Ramp completed
x  |  April 4, 2023 – Northwest section, rebar for Grade Beam now in place
x  |  April 4, 2023 – Northeast side ready to receive waterproofing
x  |  April 12, 2023 – Grade Beam rebar placement for pour 2 completed
x  |  April 12, 2023 – Pour 3 Grade Beam waterproofing completed
x  |  April 12, 2023 – Waterproofing for Stormwater tank floor completed
x  |  April 17, 2023 – Additional Rebar now being placed for the final ramp section towards the entrance off Anne Hilliard Lane
x  |  April 17, 2023 – Verticals from Ground to Level 2 starting
x  |  April 17, 2023 – North side of Pour 1 Ground Floor Slab, reveals strip footing for future parameter wall from Ground to Level 2
x  |  May 16, 2023 – Verticals are being formed from Ground to Second Level
x  |  May 16, 2023 – Ground Floor Slab now complete
x  |  May 16, 2023 – Forming in place for the East Perimeter Wall, from Ground to Mezzanine Level
x  |  May 25, 2023 – Decking to Level 2 on the West Side along Parliament Street has started. Circular columns along the South Side have been poured
x  |  May 25, 2023 – Ramp section to Ground Level completed for the vehicular entry at Anna Hilliard Lane
x  |  May 25, 2023 – Double Sided forms for the North Side Perimeter Wall in place
x  |  June 13, 2023 – Extent of Decking for Level 2 on the Southern Limit, next to the land conveyance
x  |  June 13, 2023 – Formwork for parking roundabout in place from Ground to Level 2
x  |  June 13, 2023 – Stripping formwork on the east side revealing parking access below grade
x  |  June 29, 2023 – Stripping of the roundabout leading to the Parking levels completed, Level 1 to 2
x  |  June 29, 2023 – Mechanical work started below grade, P Levels
x  |  June 29, 2023 – All conduit work for Pour 1 of Level 1 completed, awaiting concrete placement
x  |  July 7, 2023 – Current form of Parliament & Co. from Parliament Street showing verticals forms from Level 2 to Level 3 have started
x  |  July 7, 2023 – Final rebar for Level 2 has arrived, awaiting placement before the concrete pour
x  |  July 7, 2023 – Second pour for Level 2 started
x  |  July 14, 2023 – Conduit work is on-going for the last pour on the 2nd Level on the east side
x  |  July 14, 2023 – Verticals stripped on the south side from Level 2 to Level 3
x  |  July 14, 2023 – Mechanical work has started below grade
x  |  July 21, 2023 – Inside forms and rebar placement around the elevator core complete. Outer forms now being placed for concrete pour, from Level 2 to Level 3
x  |  July 21, 2023 – Southside perimeter column forms erected from Level 2 to Level 3
x  |  July 21, 2023 – Mechanical work continues, below grade
x  |  August 2, 2023 – First pour for Level 3 completed along the West Side
x  |  August 2, 2023 – Level 3 East Side floor decking and capital forming underway
x  |  August 2, 2023 – Main Level stripping of the concrete slab and reshoring
x  |  August 14, 2023 – Rebar and Conduit placement nearing completion on Level 3 East Side
x  |  August 14, 2023 – Forming Columns on Level 3
x  |  August 14, 2023 – Placing Forms for the North Perimeter Wall on Level 3
x  |  August 30, 2023 – Southwest view, showing Level 4 deck work extending north to Jessie’s Place
x  |  August 30, 2023 – View looking East, revealing the completed Level 3 above which deck forming has been completed on the South side
x  |  August 30, 2023 – South face of Parliament&Co reveals the structural columns and openings for future warehouse inspired windows
x  |  September 20, 2023 – South Elevation revealing the large expansive openings for the Warehouse inspired-windows
x  |  September 20, 2023 – North Elevation showing the garage entrance from Anna Hillard Lane
x  |  September 20, 2023 – West Elevation indicating the completion of the 4th level structural slab
x  |  September 26, 2023 – Back side of form in place and rebar erection has commenced for north perimeter wall
x  |  September 26, 2023 – Hanging pipe has now started on the main level
x  |  September 26, 2023 – 3/4 inch stone placed along the west side for future pedestrian sidewalk
x  |  September 27, 2023 – Rebar placement completed on the East Side, 5th Level Conduit work to begin
x  |  September 27, 2023 – Shotcrete on the North Perimeter Wall in progress, 5th Level
x  |  September 27, 2023 – View looking North revealing 5th Level decking progress
x  |  September 29, 2023 – Conduit work continues for the Northeast side
x  |  September 29, 2023 – Rebar placement and conduit work completed for the Southeast side, ready to receive concrete
x  |  September 29, 2023 – Shotcrete of the central northeast wall section completed, Level 3 to Level 4
x  |  October 11, 2023 – Guard rails installed in preparation of work to begin on above grade
x  |  October 11, 2023 – Piping installation continues below grade
x  |  October 11, 2023 – Block work started below grade
x  |  November 13, 2023 – Top and Bottom Rebar placement continues for 7th Level Slab
x  |  November 13, 2023 – Steel HSS work has started, fastened below the 2nd Level Slab
x  |  November 13, 2023 – Masonry block work continues on Level P1
x  |  December 6, 2023 – HSS work along the Eastside perimeter wall completed on Level 2
x  |  December 6, 2023 – Decking and placing bottom rebar continues for Level 8. Conduit works initiated
x  |  December 6, 2023 – Duct work well underway below grade, along with hanging pipe for drains and erecting masonry block walls
x  |  January 30, 2024 – DensGlass on steel stud installation started on the sixth level, facing North and West
x  |  January 30, 2024 – Hoist installation complete on the North side entrance off Anna Hilliard Lane
x  |  December 6, 2023January 30, 2024 – Steel stud erection on the perimeter of the 6th Level completed, image shown is facing south
x  |  March 8, 2024 – Densglass and Blueskin work on the perimeter has started
x  |  March 8, 2024 – Curtain wall window frames have started on the main level
x  |  March 8, 2024 – South facade revealing the progress with Densglass and Blueskin
x  |  March 18, 2024 – Densglass applied on the north side, 3rd level terrace section
x  |  March 18, 2024 – Riser connection work continues above grade
x  |  March 18, 2024 – Painting has started below grade